Brief

Mill Court was engaged to produce an Independent Expert Report on Defined Cost under an NEC Option C Target Cost reimbursable contract for the enabling works.

What we did

We completed a full cost audit of the contractor including auditing its supply chain at each office, to identify costs not entitled to be claimed under the contract and prepared a separate claim for disallowed costs against the contractor.   

Outcomes

Identified a significant amount of incorrectly claimed costs and properly re-valued claims for compensation by correctly applying the contract mechanism.